When it comes to USCO® switches, we have a rigorous process to provide a top quality product. Reviews, design, approvals and manufacturing all go into product lead times.
Day 0
Receive Purchase Order from Customer; Customer Service enters into SAP system
Day 7
Engineering and Marketing Review Complete
Day 10
Assigned to Designer
Day 31
Approval Drawings sent to Customer for Review/Approval
Day 45
Receive Final-Approved Drawings from Customer
Day 46
Final Changes
Day 49
Released to Production
Day 77
Current Promised Ship Date
*Time is based on calendar days